- The implementation of which of the following processes decreases the risk of project failure?
-
Manage stakeholder engagement
-
Control stakeholder engagement
-
Plan stakeholder management
-
Develop stakeholder engagement
CORRECT:
A - Manage stakeholder engagement decreases risk of project failure.
- The five levels of stakeholder engagement are...?
-
Oblivious, opposed, neutral, proactive, driving
-
Unaware, opposed, neutral, supportive, driving
-
Oblivious, resistant, neutral, supportive, leading
-
Unaware, resistant, neutral, supportive, leading
CORRECT:
D - The correct selection is: Unaware, Resistant, Neutral, Supporting, Leading.
- Plan stakeholder management is fundamentally concerned with all the following except...?
-
Developing strategies to effectively engage stakeholders throughout the project
-
Development of the stakeholder register
-
Development of the stakeholder management plan
-
Identifying how the project will affect stakeholders
CORRECT:
B - The stakeholder register is created in the Identify Stakeholders process.
- You are engaged in gathering information from stake holders regarding whose interests should be taken into account throughout the project. This is called:
-
Identify stakeholders
-
Stakeholder analysis
-
Expert judgment
-
Plan stakeholder management
CORRECT:
B - This is called a stakeholder analysis.
- Which of the following is not included in the Stakeholder Management Plan?
-
Project lifecycle
-
Communications requirements
-
Impact of scope changes to stakeholders
-
Stakeholder management strategy
CORRECT:
A - The project lifecycle is selected and defined in the project management plan.
- Most projects will have a ___________ number of stakeholders.
-
Resistant
-
Supportive
-
Diverse
-
Unknown
CORRECT:
C - A diverse number of stakeholders.
- Which of the following is not an input to the Control Stakeholder Engagement process?
-
Project management plan
-
Issue log
-
Project documents
-
Work performance information
CORRECT:
D - Work performance information is an output of control stakeholder engagement.
- The ability of stakeholders to influence the project is typically highest at the _________ stages.
-
Planning
-
Initial
-
Executing
-
Design
CORRECT:
B - the initial stages.
- The three 'I's' of stakeholders are...?
-
Independence, influence and inquiry
-
Importance, inquiry and influence
-
Interest, influence and importance
-
Influence, inquiry and importance
CORRECT:
C - Interest, influence and importance.
- A stakeholder is...?
-
Anyone who is involved in the project
-
Anyone positively or negatively impacted by the project
-
Anyone who can influence the direction of the project
-
Anyone who can impact/be impacted positively or negatively by the project
CORRECT:
D - Anyone who can impact/be impacted positively or negatively by the project.